HAN-TEK project featured in HOIST Magazine
Glass producers are increasingly demanding larger and larger refractories
for their furnaces. Refractories are the linings for the furnaces, made
of a material such as alumina, zirconia and silica to withstand high
temperatures. One such producer, Vesuvius Monofrax, based in New York,
USA, needed a new crane to work with its own furnace. Refractory producers
use furnaces as well as supply them, to melt down the raw materials.
The molten refractory material is then poured into moulds to create
bricks that are used for the furnace lining.
The existing 7.5 US ton SWL single girder stacker crane was nearing
the end of its useful life and required excessive maintenance. More
importantly, it was no longer big enough for the size of refractory
being demanded by its customers. A double girder stacker crane is the
standard solution to the problem, but such a design would have proved
too big for the existing facility, and building redesign would have
been too expensive.
Instead, HAN-TEK engineered and installed a single girder stacker crane
with an SWL of 15 US ton (13.5t) to work around the clock. "This
crane and the furnaces it supports are the backbone of Vesuvius Monofrax's
business," says a HAN- TEK spokesman. Existing runway girders and
columns had to be reinforced to bear the increased wheel loads imposed
by the larger crane. AceWorld Companies of Texas designed and built
the crane and carried out runway reinforcements.
The new crane allows the operator to use the forks on the mast to reach
into an area and pick up a silica mould standing up to 3m (l0ft) high.
The crane then moves along a 30m ( I00ft) runway system to one of two
furnaces. The furnace pivots to pour molten refractory- heated to 2,750°C
- into the mould. The crane then backs out, deposits the filled mould,
picks up an empty mould in sequence and moves back to the furnace, accomplishing
several pours every half hour. Forklift truck operators move the moulds
into and out of the staging area.
HAN-TEK claims that its crane system delivers greater operator control
and more precise positioning. The controls are programmed to deliver
full torque to the hoist braking system, checking for proper adjustment
a split second prior to every brake release. If any slippage is detected,
the brake will not be released. The crane also has a slack-cable detection
system that eliminates the potential for operator error when lowering
the carriage, HAN-TEK says. Variable-frequency drives are used on all
motions to give soft starts, torque proving and load float and thus
reducing wear and tear on the brakes and other mechanical components.
The drives are housed in a separate, air-conditioned enclosure. Maintenance
requirements consist primarily of regularly lubricating the moving parts
and checking the wire rope and bearings for wear, says HAN-TEK. The
less downtime there is on the stacker crane, the more refractory bricks
can be produced.
The operator can control the crane either from a festooned pendant
station or at one of two pedestal-mounted control stations at the furnaces.
Fibreoptic cables connect hoist encoder to the crane's drives.
Project planning took three years, but installation took just three
weeks and was completed in August 2003. The cost of the project was
$950,000.
HAN-TEK (as in 'handling technology') has been in business for more
than 40 years and is a Cranemart company, part of the network of overhead
crane builders that are Columbus McKinnon distributors.